Contract to Open New Bridge – Stripe, Sign and Surface the new bridge. Switch Traffic to the new bridge and Demolish the old bridge. Contract to be let in fall of 2009. |
X |
|
|
Arkansas Approach to the Main Span Unit –
Construct 4600 feet of bridge plus connecting roadway. Work started in the spring of 2006 and completion is expected in the summer of 2009.
|
|
|
X |
Mississippi Approach to the Main Span Unit –
Construct 6500 feet of bridge plus connecting roadway. Work started in the spring of 2005 and completion is expected in the spring of 2008.
|
|
|
X |
BRIDGE SPAN COMPLETE – Final floorbeam installed in closure span; final concrete deck panels installed; final closure pours between remaining deck panels. |
|
|
X |
Piers 37-38: MAIN SPAN CLOSURE – Superstructure erection meets between bridge towers |
|
|
X |
Pier 39 Tiedown: Superstructure reaches Pier 39 (anchor pier, Mississippi shore) |
|
|
X |
Pier 36 Tiedown: Superstructure reaches Pier 36 (anchor pier, Arkansas shore)– COMPLETED JANUARY 2006
|
|
|
X |
Pier 37: Erect superstructure segments with structural steel, stay cable installation and precast concrete deck panels – (Began June 1, 2005) |
|
|
X |
Pier 38: Construct upper (plumb) tower legs – tower reaches full height (with exception of pier caps) |
|
|
X |
Pier 38: Post-tension strut and pier cap |
|
|
X |
Pier 38: Construct “bow-tie” strut between tower legs — May 2005 |
|
|
X |
Pier 38: Construct battered (inclined) lower tower legs |
|
|
X |
Pier 38: Construct pier shaft and pier cap – COMPLETED SEPTEMBER 2004 |
|
|
X |
Pier 37: Construct upper (plumb) tower legs – tower reaches full height (with exception of pier caps) |
|
|
X |
Pier 37: Construct “bow-tie” strut between tower legs – March 2005 |
|
|
X |
Pier 37: Construct battered (inclined) lower tower legs – COMPLETED NOVEMBER 2004 |
|
|
X |
Pier 37: Construct pier shaft and pier cap – COMPLETED AUGUST 2004 |
|
|
X |
Pier 36 (Arkansas shore) – Construct anchor pier for west end of bridge. PIER 36 COMPLETED NOVEMBER 2004 |
|
|
X |
Pier 38: concrete seal pour of caisson dredge wells, distribution cap at top of caisson: PIER 38 CAISSON COMPLETED APRIL 2004 |
|
|
X |
Pier 37: concrete seal pour of caisson dredge wells, distribution cap at top of caisson: PIER 37 CAISSON COMPLETED FEBRUARY 2004 |
|
|
X |
Pier 38: Excavation & sinking of caisson into river floor to predetermined elevation. Pier 38 reached founding elevation on March 13, 2004. |
|
|
X |
Pier 38: Pouring of support caisson, sinking of caisson to river bottom. Caisson reached river bottom week of October 11, 2002. |
|
|
X |
Pier 38: Cutting edge floated into place. Positioning of cutting edge into caisson guide — June 27, 2002. |
|
|
X |
Pier 37: Excavation & sinking of caisson into river floor to predetermined elevation. Pier 37 reached founding elevation on January 16, 2004. |
|
|
X |
Pier 37: Pouring of support caisson, sinking of caisson to river bottom. Caisson reached river bottom on August 9, 2002 |
|
|
X |
Pier 37: Cutting edge floated into place. Positioning of cutting edge into caisson guide — April 10, 2002 |
|
|
X |
Laying of articulated concrete mattresses on river bottom around sites of piers 37 and 38 – week of December 10, 2001 |
|
|
X |
Official groundbreaking ceremony — November 2, 2001 |
|
|
X |
Awarding of construction contract to the low bidders — July 27, 2001 |
|
|
X |
Acceptance of contractor bids for construction of bridge, MDOT Headquarters, Jackson, MS — June 26, 2001 |
|
|